(resolved) Wrong task consumption count
Status: Open · Asked by Pradeep Dodle on · 0 views
This page shows that we've already used 2661 paid tasks today (29th Nov) till 9:45AM. One particular workflow WixFix19Aug is shown to have consumed 592 paid tasks.

However, if you go to workflow level usage, it shows that this workflow has consumed only 108 paid tasks today (29th Nov) till 9:45AM.

We noticed that some workflows are running with wrong paid task count.
For example, please look at the following screenshots. It shows that these are workflows with 23 steps with only 2 free tasks. However, when we click on the task history, we see that there are 11 free tasks.
Why are we wrongly being billed here?

Hello @PradeepD
Could you please provide the email address associated with your Pabbly Connect account This will help us investigate the issue more effectively and provide you with the appropriate assistance.
Please check ticket number: 103188
Hello @PradeepDCould you please provide the email address associated with your Pabbly Connect account? This will help us investigate the issue more effectively and provide you with the appropriate assistance.
Attachments




Hello @PradeepD
We have answered your concern on the same ticket ID - 103188. Please refer to it for further discussion.
Thanks Preeti